|
August 2007
Toccoa Tailwater
Status Report
During their July program, members of the Blue Ridge Mountain Chapter of TU
were relieved to learn that the fish they pursue in the Toccoa tailwater are
not likely to suffer any adverse impact during the impending deep draw-down
of Blue Ridge Reservoir. However, while the trout will be “happy” with
conditions on the tailwater, anglers may not be all the time. In all
likelihood, juggling fishing outings around a TVA generating schedule that
places little priority on anglers’ desires is going to continue.
This information came from Dr. Wayne Poppe, TVA’s Senior Manager of River
Operations, who
|
 |
|
Wayne Poppe explains
TVA generating procedures to Blue Ridge Mtn. TU chapter members at the
July 14 program. |
met
with the Blue Ridge TU group on July 14 when Poppe said the TVA is
struggling to operate its reservoirs in the Tennessee River System through
the worst drought that has occurred during the 118 years that records have
been kept. Poppe said extremes in weather – drought or flood – present
challenges for managing the flow of water through the system, but droughts
are the most frustrating. “A flood is like the flu – it comes on fast, is
bad for a few days, but then its gone, “ Poppe said. “But a drought is like
a migraine headache that just won’t go away.” Recent rains have helped the
situation, he said, but lake levels have already been affected to the point
it’s going to take time to recover.
Poppe reported that a long-term work project involving renovations to the
Blue Ridge dam that was constructed almost 100 years ago is continuing. So
far a spillway was added at the dam in 1993 and a low-level outlet put in
during 2004 which consists of a 1,000-foot-long 12-foot-diameter tunnel
drilled through the bedrock underneath the earthen dam. The next, and final
phase, of the project will be a deep draw-down of the reservoir so three
objectives can be accomplished: 1) repairing the penstock that buckled when
the lake originally filled; 2) stabilizing the intake tower located in the
lake just out from the dam by adding more concrete to the structure; and 3)
adding mass to the dam on both the “upstream” and “downstream” sides to
bring it up to today’s safety standards.
Poppe said right now, it is not known when the deep draw-down will begin. He
said TVA is in the design phase now and this will take at least until late
winter to complete. At that time, the designs will be reviewed by various
parties to make sure the engineering and plans are optimum, followed by any
revisions that may be necessary. Then the project will go to the contract
development and financing phases before actual construction will ever start.
With all that must be done, Poppe said he would not even venture a guess on
when the draw-down will start.
However, he did say that as far as maintaining water quality in the
tailwater during the project goes, “I don’t see any issue with this. If you
are a trout, you’ll be happy.”
While he will not know exactly how low the lake level will go during the
deep draw-down until the design plans for the renovations are completed, it
won’t be a situation where the river is running unchecked across a then
exposed lake bed. A weir dam will be constructed around the penstock work
area and he expects water levels will remain at depths that maintain a
thermocline for cold water releases. Even when the water is exiting the dam
through the low level discharge rather than the generator, it will be
oxygenated by an aeration system built into the release system valves. Poppe
said minimum flows would be maintained, not just for the biological health
of the river, but also to keep the intake pipes covered with water for the
three municipal water systems that draw from the Toccoa tailwater.
|
 |
|
Wayne Poppe shared
this old photo of a workman checking out the buckled pinstock years ago.
Repairs to the pinstock will be one part of an extensive work project at
Blue Ridge Dam coming up sometime in the future. |
Another bit of good information for anglers shared by Poppe is that a
tailwater generation warning system will be funded and installed by TVA
during FY08. Poppe said TVA is looking at warning systems for all their
dams. He said plans vary from dam to dam due to topography and other factors
and the system that will be installed at Blue Ridge Dam has not been
developed yet, but it will include audio and visual alerts that generation
is beginning.
The
news was not as good for anglers concerning the information Poppe shared
about TVA generating schedules. Rather than giving much consideration to
fishermen having Saturday mornings on the river with minimum flows, TVA
operates the generators strictly based on electrical load management of
their power grid, Poppe said. He said this is partially based on providing
the electricity demanded by the 8-million consumers who get their power from
TVA facilities, but also on voltage load maintenance on the system. Poppe
said this latter factor (which he explained in lots more detail) is more of
a factor in setting generation schedules for the facilities on the fringes
of the system like Blue Ridge.
While load management trumps other factors as far as generating times go,
Poppe pointed out that TVA is concerned about environmental factors –
including trout habitat – in the tailwaters. He said across the TVA system
millions of dollars have been spent to upgrade water quality. These measures
include such things as the oxygenation system at Blue Ridge dam and the
“little generator” that ensures a minimum flow down the tailwater.
The
Blue Ridge Dam generating schedule is also not geared around the Ocoee
rafting interests, according to Poppe, reiterating that load management has
the highest priority. He said minimum flow from the Blue Ridge Dam is
capable of providing the amount of water needed for rafting on the Ocoee. He
said there is a contract between the TVA and the whitewater industry to
provide specified flows, but this is to compensate TVA for the loss of
electricity that occurs when water is released for whitewater recreation
rather then generation. From a holding reservoir near Copperhill, water is
spilled directly into the Ocoee for whitewater purposes, Poppe said, rather
than being run through the flume to the generators at Ocoee #1 and #2. “We
can’t generate when the rafters are riding,” Poppe said.
As
for deviations from the posted generating times on the toll-free phone
system and the internet, Poppe said there is no way to anticipate all the
system-wide factors that may necessitate last-minutes changes and these
should always be anticipated. He said because there will always be
unannounced generating periods, the TVA considered not even publicizing the
planned schedules. But for the most part, the schedules are followed and
river users can make plans based on them while remaining alert to the
warning they hear on the phone and read on the internet: “Please note! Use
caution near dams. Water release schedules often change without notice due
to unanticipated changes in weather conditions and power system
requirements.”
This was the second time in recent years that Dr. Poppe has presented the
Blue Ridge TU Chapter’s program and both times resulted in those present
receiving much good information about the TVA in general and the Toccoa
tailwater in particular. |